Standardizing processes across multiple plants to support mass customization
23% increase in throughput.
What we walked into.
The transportation equipment manufacturer was encountering problems up and down their production process in five plants. The CEO tasked Maine Pointe to fix problems related to engineering, bill of material (BOM), and scheduling challenges, in order to reduce stress on the workforce, free up capacity, and provide room for growth.
The five plants had all been acquired over time and had a history of competing with each other. The plants lacked standardization in everything from specifications to materials and flow. Therefore, quality varied greatly from plant to plant. Operators were used to making adjustments to materials on the fly (for example, by cutting material to the length they needed), which made inventory control difficult. These problems were exacerbated by unreliable delivery from suppliers.
How we delivered.
- Integrated systems across multiple functions
- Evaluated footprint scenarios, including consolidation of sub-assembly manufacturing to free up floor space
- Eliminated significant non-value time and improved safety by having materials delivered and staged at the line, delivering the parts exactly when and where needed
- Conducted geo-mapping of orders by plant, customer, and end user to rationalize order allocation
- Set up a process and dashboard to track production stages and ensure completion before customer delivery
- Reduced time that product sat on the shop floor (dwell time)
- Acted as an accelerator for the company’s IT team in data analysis and creating analytic tools
What got delivered.
- 23% increase in throughput
- 40% decrease in dwell time
- 40% decrease in schedule changes
- 20% capacity gain
- Released $5M in cash
- Drove accountability by creating tools to standardize and visualize scheduling, routing, and operations processes
- Performed bill of material (BOM) review
- Improved inventory accuracy
- Led way to future production optimization and standardization
More case studies
All results →
Reaching refinance and exit goals by reducing costs and optimizing the supply chain
Improved profitability by 10%.

Expediting goal to double revenue with focus on throughput
Increased production throughput 14%.

Reducing variability in the line and boost throughput with innovative tools and processes
Decreased schedule changes 11%-19% within three months.