Expediting goal to double revenue with focus on throughput

Increased production throughput 14%.

Read the full case study →
The challenge

What we walked into.

A leading manufacturer of cables and cable systems faced a mandate to double in size within 5 years, increasing revenue from nearly $200M to more than $400M with half the growth coming organically. The company’s executive leadership wanted to understand what locations should be considered for growth in warehousing and manufacturing facilities, to improve costing and customer service.

The approach

How we delivered.

  • Instituted hot handoffs between shifts to keep machines running at speed with minimal downtime
  • Set up a Daily Schedule Control (DSC) process that increased running speeds
  • Closed disconnect between HR, operations, leadership, and manufacturing floor with DSC, and Plant Improvement Plan
  • Provide executive leaders with more visibility into manufacturing and ability to meet goals
The outcome

What got delivered.

  • Increased production throughput 14%
  • Gained $3M to $5M in incremental profit
  • Delivered 5:1 ROI in year one
  • Modelled network for data-based decision making on expansion options
  • Implemented more than 20 safety, onboarding, training, and productivity improvements
  • Provide standard manufacturing procedures and increased visibility
  • Undertook second phase of project, budgeting and overseeing physical move