The maintenance report says the fleet is available. The production report says the shift missed its target. Both can be correct. An excavator can be mechanically ready while its operator is elsewhere, its work area is inaccessible or the haul route cannot absorb its output. The leadership mistake is to treat these as separate departmental problems. Productive work begins only when equipment, people, parts and the operating sequence are ready together.

Separate availability from an executable shift

Mechanical availability answers whether an asset can operate. Utilization asks whether it actually operates. Productivity asks what useful work it completes while operating. Those distinctions matter because the remedies differ. A maintenance intervention will not resolve a delayed permit or a missing operator. Asking maintenance to solve every production shortfall can improve its dashboard while leaving the mine's constraint untouched.

Start the shift review with the planned work, not the fleet total. Identify the asset and crew combinations required for each activity. Then confirm access, fuel, service support and downstream capacity. A spare truck has little immediate value when the constrained activity requires a particular excavator attachment. Readiness must be attached to a task and a time, rather than recorded as a general condition.

Treat critical spares as operating decisions

Inventory policies often penalize a part for moving slowly without asking what happens when it is absent. At a remote mine, an infrequently used component can protect a critical operation. Conversely, a heavily stocked item may offer little protection if the repair requires a specialist who is not available. Criticality belongs to the failure scenario, not simply to the item number.

  • Identify the production or safety consequence of the failure.
  • Check whether another asset, repair route or approved component can substitute.
  • Include diagnosis, transport, repair and installation in the recovery pathway.
  • Confirm the tools, skills and access required to use the spare.
  • Assign ownership for reviewing the policy when equipment or mine sequences change.

This changes the discussion between finance and maintenance. The question is no longer whether inventory should rise or fall everywhere. It is where cash protects a meaningful exposure and where stock has accumulated without a credible operating purpose. Repairable components also need a visible return loop. A component awaiting inspection at a vendor is not equivalent to a serviceable spare on site.

Make the handoffs visible

The most revealing failures often sit between functions. Maintenance completes a repair but the equipment misses dispatch. Engineering releases an area after the contractor has reassigned its crew. A shift receives the right part without the tools needed to install it. Each team can report completion while the operating system remains incomplete. Track handoffs explicitly, including who accepts readiness and what evidence they need.

A shared lookahead should expose unresolved dependencies before they become shift losses. Supervisors need authority to flag work as not ready without being accused of withholding production. Contractor participation matters because the mine's plan may rely on resources controlled by another organization. Safety controls remain prerequisites; pressure to recover a schedule must not redefine an unsafe task as executable.

Digital analysis can help explain recurring losses, but it cannot substitute for field verification. Maine Pointe's Combined Intelligence model is human-led, AI-enabled: work-order narratives and shift records can reveal patterns for a superintendent to investigate. The responsible leader validates the cause and approves the response. An apparent equipment problem may actually be a coding habit or an inaccessible work area.

What to do next: test readiness against actual work

Choose a constrained operating activity and reconstruct its recent missed starts. Follow each loss across maintenance, labor, materials and work-area readiness. Do not accept a broad category such as operational delay as a root cause. Establish which decision could have changed the outcome, when that decision was possible and who had the information needed to make it.

The Mining Value Assessment provides a structured starting point. It maps site constraints, critical-spares exposure and logistics dependencies into an owned improvement backlog. Through Total Value Optimization™ (TVO™), the objective is to improve the complete operating outcome rather than optimize one function. Success is a plan the site can execute safely, supported by measures that distinguish available equipment from completed work.

David Jadwin, Managing Director
Author
David Jadwin
Managing Director — Maine Pointe
LinkedIn profile ↗
Talk to our team →

Facing this in your business?

Tell us what you're trying to fix. A partner who has done it before will come back to you.

Talk to a partner